Mott MacDonald is working in partnership with the
Director of Planning and Transportation, Norfolk County
Council on the above scheme. The works are proposed
to take place starting Monday, 3rd March 2003 and
complete on or before 24th April 2003. The works comprise
the excavation and installation of a new culvert under
the B1354 (Wroxham Road) in Coltishall adjacent to
the Kings Head and Rising Sun public houses.
To carry out the works it will be necessary to manage
traffic for the full duration of the construction
works. This traffic management will take the form
of one way lights and a 20 mph speed limit for the
majority of the works with a full closure limited
to two weeks which will prevent traffic from using
the B1354 over the culvert. The road closure will
be removed from the works before the Easter period.
The diversion route is via the Al151, the A1142 and
the B1150.
If you have any comments relating to the scheme please
do not hesitate to contact Mr Tim French on
01603 767530.
|